CHSI Middlemore Hospital
Otahuhu, Auckland
Client / Builder –
Arrow International Ltd
Systems Installed:
MAGE back ventilated cladding support system and Fundermax Exterior HPL – High Pressure Laminate exterior cladding panels. Note: 15 individual colours were used on this project.
Installation Methodology:
MAGE aluminium brackets, T and L profiles were installed to form both the structural support system and the back ventilated / drained cavity. MAGE MG-Fix brackets, T and L profiles were set out and installed on the Rigid Air Barrier provided by the builder. The combined use of MAGE MG-Fix brackets and profiles provided and adjustable structural support system designed to cater for construction tolerances. Brackets and profiles were installed in strict accordance with MAGE engineered design.
Note: This project employed the use of XPS 50mm closed cell foam insulation installed on the outside of the Rigid Air Barrier, within the 70mm cavity.
Fundermax HPL cladding panels were site measured, cut and prepared offsite in the Insite Facades factory, then installed on site using colour matched rivets to attach cladding panels to pre-installed aluminium profiles.
Installation Team: 4 - 6